One of Europe’s most demanding cold chain logistics facilities — delivered turnkey in just 6 months













Design, supply, and install a complete temperature-controlled logistics facility in Castanheira do Ribatejo. The turnkey project encompassed multiple frozen and chilled storage chambers alongside dedicated loading dock areas for both positive and negative temperature operations — all delivered within a 6-month timeframe. The solution was engineered to meet strict thermal performance and operational requirements, ensuring long-term reliability across the full cold chain.
Business unit
Food Chain & Logistics
Project Scale
A full turnkey cold storage facility spanning approximately 19,520m² of insulated panels, across frozen chambers, chilled chambers, and dual-temperature loading docks.
Products
Insulated Panels — Approximately 19,520m² installed across all chambers and dock areas, optimised for thermal efficiency and durability.
High-Speed Doors — 12 units installed to support fast-moving logistics operations while minimising temperature loss.
Hinged (Pivot) Doors — 16 units installed across chambers and access points.
Sliding Doors — 6 units installed for loading dock access
Frozen Storage
Three frozen chambers with a combined area of 3,835m² and a total volume of 46,380m³, designed for high-capacity negative temperature logistics operations.
Loading Dock Capacity
Dedicated loading areas for both positive and negative temperature operations, totalling 1,440m² — designed to support high-throughput logistics workflows.